Agency said 'revision rounds are over, we won't accept further requests' — do they have the right?

CCem B***MemberCommunity member
Joined
Jun 2022
Message
316
#1

contract: 'two revision rounds included.' we finished the first round, it went well. in the second round i added other requests this time — text changes, image shifts, etc. the agency said 'rounds are over, anything after this is chargeable.'

but in the second round i listed requests we hadn't fully done as missing. for example 'this button doesn't open properly here, can you fix it?' — this isn't a new request, it's a bug fix. the agency says 'it's all the same thing,' but technically it's different.

it always gets messy. what is a revision, what is a bug, what is an 'extra request'? is a text change on a site a revision or an extra? is the agency right to ask for money, or should it be covered by the quote?

AAycan D***MemberCommunity member
Joined
Oct 2024
Message
240
Most Helpful#2

you need to separate them: 'revision' = design/layout change. 'bug' = something you did wrong that needs fixing (this doesn't count as a revision). 'extra request' = something new.

it should be written in the contract: 'revision rounds correspond to design changes. bug fixes and technical issues are not included in revision rounds.' this way the agency has to fix bugs for free.

if you reported a bug in the second round, that doesn't count as a revision. if you added another design request, that counts as a revision. these are two different things. send a written report to the agency: 'this is a bug not a revision, can you fix it quickly?'

CCeren K***MemberCommunity member
Joined
Jan 2023
Message
377
#3

mine was very similar too. in the end i bargained, i said 'either finish this round for free, or i'll give it to someone else.' the agency agreed and finished it.

NNeslihan A***New member
Job title
Company Owner
Sector
Plastic
Organization type
chain store
Joined
Aug 2026
Message
4
#4

when the agency says "rounds are over," they might just be stringing you along to charge extra fees. honestly, "2 revisions" is totally enough for a simple site. if you've got 100 requests in 3-4 weeks, that's not a revision issue, that's just how the project is structured.

HHasanMember
Job title
WordPress developer
Joined
Nov 2023
Message
152
#5

send an email right away: "the following 3 items are technical issues and bugs, not revisions:" and make a list. the agency will see you're right and fix them for free.

RRecep B***ExpertCommunity member
Joined
Jun 2024
Message
111
#6

maybe the agency is just in a rush to finish and move on (waiting for another project). easy solution: say "if you finish the remaining work from this round by Wednesday, I'll pay an extra fee." they usually speed up when money is involved.

ZZübeyde Ç***Member
Job title
Finance Manager
Sector
Logistics
Organization type
chain store
Joined
Jan 2026
Message
94
#7

i was stuck in the same situation, then i asked "does this count as a bug?" they said "yes, its a bug fix." so the issue stayed within the round and they continued... basically, ask seriously about the nature of the issue.

MMuhammetNew member
Job title
Association manager
Joined
Oct 2024
Message
34

Doki · Corporate website · 2025

#8

you're right.

FFerhat A***ExpertCommunity member
Joined
Mar 2026
Message
124
#9

This is exactly what we experienced. If it's your first time, start small; scaling comes later.

If scope grows, either time or budget must grow. There is no third option. If you have questions, write them; I'll answer as best I can.

GGürkan D***Member
Job title
Human Resources Specialist
Sector
Plastic
Organization type
300-person organization
Joined
May 2023
Message
362
#10

We need to take it step by step. Most time waste accumulates in tasks waiting for approval.

This is my opinion, I'm not claiming it's absolute truth.

SSelim K***MemberCommunity member
Joined
Jan 2023
Message
147
#11

I've been dealing with this for a long time. People defend habits, not processes. Resistance comes from there.

In legacy systems, the most expensive thing is unknown dependencies.

ZZeynep Z***Member
Job title
Customer service representative
Sector
Law
Organization type
120-person company
Joined
Jan 2023
Message
1
#12

let me share my experience... if acceptance criteria aren't written when the work is done is open to debate.

RReyhan K***Member
Job title
IT manager
Sector
Electrical-electronics
Organization type
regional distributor
Joined
Apr 2023
Message
93
#13

I have an objection here. If acceptance criteria aren't written, when the work is done is open to debate.

Correct me if I'm wrong.

MMehmet Ç***MemberCommunity member
Joined
Apr 2023
Message
277
#14

Absolutely. If I were to add anything: If you dont write this down from the start it leads to arguments later.

MMert P***Expert
Job title
Front office accounting
Sector
Energy
Organization type
regional distributor
Joined
Sep 2022
Message
204
#15

I'll argue the opposite, don't get mad. Hasty decisions become decisions you have to fix six months later.

If I were you, I'd go this route.

FFerhat O***Member
Job title
Software team lead
Sector
Packaging
Organization type
20-person company
Joined
Sep 2023
Message
52

Doki · Infrastructure migration · 2024

#16

I went through the same thing two years ago. The answer varies greatly by industry; there is no one-size-fits-all rule.

Of course, it varies if your situation is different.

OOnur S***Member
Job title
System support specialist
Sector
Packaging
Organization type
300-person organization
Joined
Jul 2025
Message
14
#17

Quick summary for newcomers: If you don't write this down from the start, it leads to arguments later.

When making decisions, write down the worst-case scenario too, not just the best. Just leaving this note it might be useful.

İİsmail Ç***Expert
Job title
Content Editor
Sector
Retail
Organization type
8-person team
Joined
Mar 2024
Message
92

Doki · E-commerce infrastructure · 2024

#18

I think it's hard to be that definitive about they said revision rounds are over. The cheapest quote is usually the least thought-out one.

Good luck with that.

EEbru K***Member
Job title
Human Resources Specialist
Sector
Furniture manufacturing
Organization type
sole proprietorship
Joined
Oct 2024
Message
105
#19

I've been dealing with this for a long time. Mistakes made on the they said revision rounds are over side are usually reversible but expensive.

BBurcu A***MemberCommunity member
Joined
May 2024
Message
146
#20

The opposite happened to me, that's why I'm writing. Start with a small trial; don't commit to everything at once.