Took 10 projects at once in my architecture office, all delayed, clients got angry — how do I set the project schedule?

ÖÖmer I***MemberCommunity member
Joined
Nov 2024
Message
1
#1

i own an architecture office, been doing this for 8 years. good projects started coming with a good option, so i said 'take them', took 10 projects at once. each project 40k TL, so 400k revenue. but i COULDN'T handle it.

i said each project shouldn't take 4 months but: the first project took 7 months, client asked 'professor why isn't it done'. i was stuck in the middle. when i started the second project, the previous designs were done but couldn't render. i had no team, i was rendering our work myself, took 3 days. currently my capacity is 30% used but clients don't understand, ask 'why is the space finished'.

now i understand: i'm a solo architect, can't manage 10 projects at once. i can do 3-4 projects at a time. yet i took 10 for the money. my clients got angry, one wrote 'bad architecture office' on Instagram.

OOya K***MemberCommunity member
Joined
Aug 2024
Message
337
Most Helpful#2

These kinds of questions are always the same: decide, do, either succeed or fail.

İİlker K***Member
Job title
Information Security Specialist
Sector
Glass
Organization type
a company within a holding
Joined
Jul 2025
Message
185
#3

To do this job: 1) Ask the client. 2) Get the answer. 3) Do it. Easy.

NNagihanMember
Job title
Recruitment Specialist
Organization type
workshop
Joined
May 2024
Message
98
#4

Standard method: Set a 'standard duration' for each job, write it to the client. Follow up.

İİbrahim Y***MemberCommunity member
Joined
Feb 2026
Message
3
#5

this job is a waste... i'm with you on this one... don't interfere just keep going.

ZZeynep A***MemberCommunity member
Joined
Sep 2023
Message
1
#6

bro this is an amazing opportunity! go now and use it 100%!

TTuğçe B***Member
Job title
Intern
Sector
Sports and fitness
Organization type
family business
Joined
Apr 2023
Message
169
#7

If customer satisfaction is the priority, you can find clients who pay a bit more. But you need patience.

YYağmur P***Expert
Job title
Customer Relations Manager
Sector
Electrical-electronics
Organization type
120-person company
Joined
Jun 2025
Message
405
#8

Due to regulations: your business needs to have these and those permits. Ask your accountant.

PPınar Y***Expert
Job title
Technical service technician
Sector
Chemistry
Organization type
40-person manufacturing company
Joined
Apr 2024
Message
277
#9

let me summariez whats been said so far then most time waste accumulates in tasks waiting for approval.

extending terms makes cstomers happy but turns you into a financing institution. like good luck with that.

HHavva Ö***MemberCommunity member
Joined
Aug 2025
Message
25
#10

Don't miss this: The answer varies greatly by industry; there is no one-size-fits-all rule.

When making decisions, write down the worst-case scenario too, not just the best. Of course it varies if your situation is different.

BBeyza T***Member
Job title
Accounting Manager
Sector
Packaging
Organization type
120-person company
Joined
Sep 2022
Message
49

Doki · Interface design · 2023

#11

I have a question, don't want to go off-topic though. If you get three different answers on a topic, the question was asked wrong.

When the closure decision was made is as decisive as the decision itself.

HHalilMember
Job title
Supply chain
Joined
Dec 2023
Message
114
#12

I partly agree, partly disagree. Mistakes made on the architecture project management side are usually reversible but expensive.

NNuri E***Expert
Job title
General coordinator
Sector
Leather
Organization type
regional distributor
Joined
Feb 2023
Message
386
#13

Exactly, and not many people know this. Any unwritten clause becomes a point of disagreement later, as both sides remember it differently.

Any unwritten clause becomes a point of disagreement later, as both sides remember it differently. Of course, it varies if your situation is different.

NNecati B***Member
Job title
Intern
Sector
Cleaning services
Organization type
8-person team
Joined
Sep 2024
Message
44
#14

I think differently. Any unwritten clause becomes a point of disagreement later, as both sides remember it differently.

ZZeynep T***MemberCommunity member
Joined
Sep 2024
Message
17
#15

Generally correct, but one part is missing. Just because everyone does it doesnt mean its right.

If you have questions, write them; Ill answer as best I can.

ÜÜlkü K***Member
Job title
Board member
Sector
Agriculture
Organization type
cooperative
Joined
Jan 2025
Message
19

Doki · Infrastructure migration · 2025

#16

The opposite happened to me, that's why I'm writing. If you don't write this down from the start, it leads to arguments later.

Processes without records never improve, because you don't know what to fix. Just leaving this note, it might be useful.

BBurcu E***Member
Job title
Administrative manager
Sector
Real estate
Organization type
40-person manufacturing company
Joined
Feb 2023
Message
37
#17

Correct.

SSenaMember
Job title
Graphic Designer
Organization type
two-branch business
Joined
Jul 2024
Message
86
#18

same here.

GGizem E***ExpertCommunity member
Joined
Jun 2023
Message
48
#19

I agree, and I'd like to emphasize that... I mean if it's your first time, start small; scaling comes later.

If it's your first time, start small; scaling comes later. If you post the result here, it will help others too.

DDoruk T***Veteran
Job title
Human Resources Specialist
Sector
Furniture manufacturing
Organization type
8-person team
Joined
Sep 2025
Message
2
#20

I'm curious too.

This topic has been closed.The moderator marked the topic as resolved. If you have a similar issue, you can open a new topic.